The effect of systemic errors on optimal project buffers
The effect of systemic errors on optimal project buffers
复制标题
DOI:
10.1016/j.ijproman.2004.12.004
复制
发表时间:
2005-05
影响因子:
8
通讯作者:
D. Trietsch
中科院分区:
文献类型:
--
作者:
D. Trietsch
Existing mathematical models for setting buffers for time or cost in project management assume that project activities are statistically independent. This leads to a highly counterintuitive and damaging conclusion that project buffers should become relatively negligible for projects with long chains of activities. We present a model that considers the statistical dependence between activities caused by estimation bias. We show that if relatively high service levels are desired, this imposes a positive lower bound on the buffer as a data-based fraction of the estimated project duration or budget. We also introduce a new approach for collecting data and estimating the parameters necessary to implement the model. This approach places a smaller burden on decision makers than traditional PERT: they provide single point estimates for means, while variance elements and bias correction are computed electronically using historical data.