A proposal for the improvement of project's cost predictability using EVM and historical data of cost
A proposal for the improvement of project's cost predictability using EVM and historical data of cost
复制标题
利用 EVM 和成本历史数据提高项目成本可预测性的建议
DOI:
10.1109/icse.2013.6606740
复制
发表时间:
2013
期刊:
影响因子:
--
通讯作者:
A. D. Souza
中科院分区:
文献类型:
--
作者:
A. D. Souza
This paper proposes an extension of the Earned Value Management - EVM technique through the integration of historical cost performance data of processes under statistical control as a means to improve the predictability of the cost of projects. The proposed technique was evaluated through a case-study in industry, which evaluated the implementation of the proposed technique in 22 software development projects Hypotheses tests with 95% significance level were performed, and the proposed technique was more accurate and more precise than the traditional technique for calculating the Cost Performance Index - CPI and Estimates at Completion - EAC.