First Beam Commissioning of the 400 MHz LHC RF System
First Beam Commissioning of the 400 MHz LHC RF System
复制标题
400 MHz LHC 射频系统第一波束调试
DOI:
--
复制
发表时间:
2008
期刊:
影响因子:
--
通讯作者:
J. Tückmantel
中科院分区:
文献类型:
--
作者:
A. Butterworth;U. Wehrle;D. Valuch;L. Arnaudon;Frode Weierud;P. Maesen;E. Shaposhnikova;J. Molendijk;F. Dubouchet;P. Baudrenghien;E. Ciapala;T. Linnecar;T. Bohl;O. Brunner;M. Angoletta;W. Höfle;J. Tückmantel
Hardware commissioning of the LHC RF system was successfully completed in time for first beams in LHC in September 2008. All cavities were conditioned to nominal field, power systems tested and all Low level synchronization systems, cavity controllers and beam control electronics were tested and calibrated. Beam was successfully captured in ring 2, cavities phased, and a number of initial measurements made. These results are presented and tests and preparation for colliding beams in 2009 are outlined.