Production rescheduling for machine breakdown at a job shop
Production rescheduling for machine breakdown at a job shop
复制标题
DOI:
10.1080/00207543.2011.579637
复制
发表时间:
2012-01-01
影响因子:
9.2
通讯作者:
Jang, Jaejin
中科院分区:
文献类型:
--
作者:
Dong, Yao-Hsiang;Jang, Jaejin
Rescheduling is a procedure to repair a production plan affected by unexpected disruptions. It is important because a production schedule released to a shop floor is subject to unexpected disruptions. This paper develops two novel heuristic rescheduling procedures, AWI-J and AWI-O, to minimise mean tardiness of jobs in a job shop. The procedures are based on an active schedule-generation procedure and Wilkerson-Irwin algorithm, which is well known for minimising mean tardiness of a schedule. The performances of the new procedures are compared with those of the Affected Operations Rescheduling (AOR) procedure, which is popular in the rescheduling literature. Efficiency measures such as mean tardiness, mean flowtime, and makespan, and a stability measure, deviation of new operation start times from the original start times, are used for comparison. Test results show that AWI-J improves efficiency over AOR, and AWI-O improves efficiency and stability as well.