Solving resource availability cost problem in project scheduling by pseudo particle swarm optimization

Solving resource availability cost problem in project scheduling by pseudo particle swarm optimization
复制标题

伪粒子群优化解决项目调度中的资源可用性成本问题

DOI:
10.1109/jsee.2014.00008
复制
发表时间:
2014-03
影响因子:
2.1
通讯作者:
Zhang, Tao
Zhang, Tao
中科院分区:
计算机科学3区
文献类型:
--
作者:
Qi, Jianjun;Guo, Bo;Lei, Hongtao;Zhang, Tao

文献摘要

相似文献

研究了以最小化资源可用性成本为目标的项目调度问题,目标是在截止日期前完成所有活动。活动之间存在完成-开始类型的优先关系,
This paper considers a project scheduling problem with the objective of minimizing resource availability costs appealed to finish all activities before the deadline. There are finish-start type precedence relations among the activities which require some