Scheduling UET-UCT Series-Parallel Graphs on Two Processors
Scheduling UET-UCT Series-Parallel Graphs on Two Processors
复制标题
在两个处理器上调度 UET-UCT 系列并行图
DOI:
10.1016/0304-3975(96)00035-7
复制
发表时间:
1996
期刊:
影响因子:
--
通讯作者:
E. Bampis
中科院分区:
文献类型:
--
作者:
L. Finta;Z. Liu;I. Milis;E. Bampis
The scheduling of task graphs on two identical processors is considered. It is assumed that tasks have unit-execution-time, and arcs are associated with unit-communication-time delays. The problem is to assign the tasks to the two processors and schedule their execution in order to minimize the makespan. A quadratic algorithm is proposed to compute an optimal schedule for a class of series-parallel graphs, called SP1 graphs, which includes in particular in-forests and out-forests.