A method for determining the groups of road segments to be constructed, the priority between them and the construction order of road segments within each group considering the disutility under construction

A method for determining the groups of road segments to be constructed, the priority between them and the construction order of road segments within each group considering the disutility under construction
复制标题

一种考虑在建负效用的确定待建设路段组、组间优先级以及组内路段施工顺序的方法

DOI:
10.2208/journalip.13.703
复制
发表时间:
1996
期刊:
Infrastructure Planning Review
影响因子:
--
通讯作者:
T. Chishaki
T. Chishaki
中科院分区:
--
文献类型:
--
作者:
Hiroshi Tanoue;M. Kiyota;T. Chishaki

文献摘要

被引文献

相似文献

本文介绍了两种确定待建路段组的方法,以及在考虑施工负效用的情况下,确定各组路段之间的优先级和各组路段的施工顺序。优化过程采用动态规划和随机模式开发方法。重点介绍了数学建模和求解技术。一个例子的问题,包括和说明所提出的方法的适用性。结果表明,该方法对道路网规划等多阶段决策问题具有一定的实用价值。
This paper describes two methods to determine the groups of road segments to be constructed, the priority between them and the construction order of road segments within each group considering the disutility under construction. The dynamic programming and stochastic schemata exploiter method are utilized for optimization procedure. The mathematical modeling and solution technique are emphasized. An example problem is included and illustrated for showing the applicability of the proposed methods. The results indicate that the methods are useful for the multi-stage determination problems such as the road network planning.